HUA Shuai. Numerical simulation research on the stability of transmission tower pile foundations in a karst area of Guangdong Province[J]. CARSOLOGICA SINICA, 2014, 33(1): 44-50. doi: 10.3969/j.issn.1001-4810.2014.01.007
Citation: HUA Shuai. Numerical simulation research on the stability of transmission tower pile foundations in a karst area of Guangdong Province[J]. CARSOLOGICA SINICA, 2014, 33(1): 44-50. doi: 10.3969/j.issn.1001-4810.2014.01.007

Numerical simulation research on the stability of transmission tower pile foundations in a karst area of Guangdong Province

doi: 10.3969/j.issn.1001-4810.2014.01.007
  • Received Date: 2013-08-18
  • Publish Date: 2014-03-25
  • The research on collaborative deformation of buried caves between transmission tower pile foundation in karst area occurred in Ruyuan county, Guangdong Province, China. The geological survey and drilling indicated that soils near the transmission tower are mainly alluvial silty clay, alluvial gravel, and residual silty clay. The bedrocks is predominately strongly weathered sandstone, moderately weathered quartz sandstone, limestone and carbonaceous limestone, which are generally greater than 30m in total thickness. Through drilling, nearly 10 different sizes of caves have been discovered in proximity to the tower. They are beaded or multi-layered in formation, and most are unfilled or half filled, where the overburden is normally 10-30 m, and a minimum of 1-4 m thick. The underlying caves have a large impact on the design, construction and operation of the transmission tower foundation. In order to study the stability and deformation of transmission tower foundations in this area, FLAC3D software was used for modele and calculations. By monitoring the stress, displacement and changes in the plastic zone at different positions, it showed that the stress distribution of the overlay is uniform and is minimally impacted by caves. However, the cave rock stress changes greatly. There is large bending down deformation in the roof of caves. Additionally, the bottom of the tower foundation moves down significantly, especially when a large stress loads are applied to the foundation and the cave roof, the cave roof would be unstable, leading to structural destruction of the pile foundation. The deformation characteristics of pile foundations with different rock-socketed depth indicate a positive correlation between rock-socketed depth and cave deformation.

     

  • loading
  • [1]
    陈国亮.岩溶地面塌陷的成因与防治[M].北京:中国铁道出版社,1994:10-15.
    [2]
    李聪林.桥梁岩溶地基的处理方法[J].桥梁,2003(1):17-18.
    [3]
    王吉英.关于岩溶地区桩基设计的探讨[J].北方交通,2007,(12):18.
    [4]
    唐辉明.工程地质学基础[M].北京:化学工业出版社,2008:8-18.
    [5]
    李前银.在论岩溶塌陷的形成机制[J].中国地质灾害与防治学报,2009,20(3):52-55.
    [6]
    赵明华,袁腾方,黎莉,等.岩溶区桩端持力层岩层安全厚度计算研究[J].公路,2003,(1):124-128.
    [7]
    程哗.岩溶区高速公路路桥基础稳定性评价方法与应用研究:[D].湖南:湖南大学,2005.
    [8]
    曹文贵,程晔,赵明华.公路路基岩溶顶板安全厚度确定的数值流形方法研究[J].岩土工程学报,2005,27(6):621-625.
    [9]
    周建普,李献民.岩溶地基稳定性分析评价方法[J].矿冶工程,2003,23(1):4-7.
    [10]
    黎斌,范秋雁,秦凤荣.岩溶地区溶洞顶板稳定性分析[J].岩石力学与工程学报,2002,21(4):532-536.
    [11]
    李炳行,肖尚惠,莫孙庆.岩溶地区嵌岩桩桩端岩体临空面稳定性初步探讨[J].岩石力学与工程学报,2003,23(4):633-635.
    [12]
    牟春梅.岩溶区地基岩体溶洞项板稳定性评价[J].西部探矿工程,2002,(4):33-35.
    [13]
    程晔,曹文贵,赵明华.高速公路下伏岩溶顶板稳定性二级模糊综合评判[J].中国公路学报,16(4):21-24.
    [14]
    钱国玉,王靖涛.宜万裸露型岩溶路基稳定性评价方法及实例[J].土工基础,2003,17(1):11-15.
    [15]
    Kumar P,Jhanwar J C,Kiran S, et al. Monitoring the stability of hydro-cavens with rock mechanics instrumentation-a case study[J]. Int. J. Rock Mech. Min. Sc,2004, 41(3):990-905.
    [16]
    Zhou Y X,Zhao J,Song H W, et al. Construction and in-stu monitoring of large-span rock cavens under favorable able stress conditions[J]. Int. J. Rock Mech. Min. Sci,2004,41(3):894-899.
    [17]
    Roberto Salvati and Ira D. Sasowsky. Development of collapse sinkholes in areas of groundwater discharge[J].Journal of Hydrology, 2002,264(1):1-11.
    [18]
    陈育民,徐鼎平. FLAC/FLAC3D基础与工程实例[M]. 北京:中国水利水电出版社,2009:14-18.
  • 加载中

Catalog

    通讯作者: 陈斌, bchen63@163.com
    • 1. 

      沈阳化工大学材料科学与工程学院 沈阳 110142

    1. 本站搜索
    2. 百度学术搜索
    3. 万方数据库搜索
    4. CNKI搜索

    Article Metrics

    Article views (1592) PDF downloads(969) Cited by()
    Proportional views
    Related

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return